[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982593":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982593,712,1,"单选题","关于项目施工阶段业主的管理工作进度控制，下列描述错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","根据项目进度总控制计划，在各专业施工与供货招标文件中明确相应的工期目标",false,{"key":16,"text":17,"correct":14},"B","编制各招标文件和合同文件中有关进度的条款，设置逾期处罚及补救办法",{"key":19,"text":20,"correct":21},"C","分析各投标单位的投标报价，必要时安排清标",true,{"key":23,"text":24,"correct":14},"D","根据情况及时调整项目进度总控制计划","C项属于项目施工阶段业主的管理工作内容中采购与合同管理的工作内容。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]