[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982591,712,1,"单选题","施工过程的目标管理，不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","目标的确定与分解",false,{"key":16,"text":17,"correct":14},"B","施工目标的实施管理",{"key":19,"text":20,"correct":14},"C","施工目标的分析与跟踪",{"key":22,"text":23,"correct":24},"D","施工目标的审查与验收",true,"业主根据工程建设项目可行性研究报告确定的总体管理目标，分解并细化施工过程的整体管理目标，确定相应的工作任务。具体包括：①目标的确定与分解；②施工目标的实施管理；③施工目标的分析与跟踪。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]