[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982589":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982589,712,1,"单选题","总价合同中的工程计量报告向()提交。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":14},"B","建筑方",{"key":19,"text":20,"correct":14},"C","设计专业人员",{"key":22,"text":23,"correct":24},"D","发包人",true,"总价合同中应约定工程计量的形象目标或时间节点，且工程计量应以经审定批准的施工图为依据。承包人在合同约定的每个计量周期内对已完工程进行计量，并向发包人提交工程计量报告，由发包人复核确认。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]