[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982587":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982587,712,1,"单选题","就大型复杂工程建设项目而言，其进度计划体系的计划构成一般不少于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","三级",true,{"key":16,"text":17,"correct":18},"B","四级",false,{"key":20,"text":21,"correct":18},"C","五级",{"key":23,"text":24,"correct":18},"D","六级","建立项目主要参与方共同编制并执行的项目现场多级进度计划体系。对于大型复杂工程建设项目，该进度计划体系一般由不少于三个层级的计划构成。第一级计划为项目进度总控制计划，第二级计划为各专业工程进度计划，第三级计划为项目短周期工程综合进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]