[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982586,712,1,"单选题","质量管理的基本模式不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","策划",false,{"key":16,"text":17,"correct":14},"B","实施",{"key":19,"text":20,"correct":14},"C","检查",{"key":22,"text":23,"correct":24},"D","反馈",true,"工程建设项目质量管理是指确立和实现质量目标的全部职能及工作内容，并对其实施效果进行评价和改进的一系列活动。质量管理的基本模式是策划、实施、检查和改进。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]