[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982585,712,1,"单选题","下列关于工程建设项目施工质量验收的说法中，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","隐蔽工程可由施工单位自行验收",false,{"key":16,"text":17,"correct":14},"B","重要的分部分项工程应由设计单位主持验收",{"key":19,"text":20,"correct":21},"C","单位工程应由建设单位主持验收",true,{"key":23,"text":24,"correct":14},"D","监理单位无权主持隐蔽工程隐蔽前的验收","AD两项，施工单位在隐蔽工程隐蔽前通知建设单位（或工程监理单位）进行验收，并按规定形成验收文件；B项，检验批、分部分项工程完成，施工单位自行验收合格后，通知建设单位（或工程监理单位）验收，重要的分部分项工程应请设计单位参加验收；C项，单位工程完工，施工单位应自行组织内部检查、评定，符合验收条件后，向建设单位提交验收申请。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]