[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982583":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982583,712,1,"单选题","实施图纸审查、工程变更和设计变更管理制度，审查承包商时，不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","审查承包商提交的各种变更、索赔、签证要求",false,{"key":16,"text":17,"correct":14},"B","及时协调解决各项变更后的利益问题",{"key":19,"text":20,"correct":14},"C","编制项目管理控制工作细则",{"key":22,"text":23,"correct":24},"D","监督项目管理承包商的采购招标",true,"图纸审查、工程变更和设计变更管理制度的协调实施。审查承包商提交的各种变更、索赔、签证要求，及时协调解决各项变更后的利益问题，使承包商能在合理的状态下施工。同时编制项目管理控制工作细则，指导监理人员实施工程变更控制。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]