[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982577,712,1,"单选题","下列关于投资回收期的说法错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","根据是否考虑资金时间价值，投资回收期可以分为静态投资回收期和动态投资回收期",false,{"key":16,"text":17,"correct":14},"B","如果静态投资回收期≤基准投资回收期，可以考虑接受项目",{"key":19,"text":20,"correct":21},"C","如果静态投资回收期＞基准投资回收期，应该接受项目",true,{"key":23,"text":24,"correct":14},"D","静态投资回收期一般以“年”为单位，自项目建设开始年算起","C项，如果静态投资回收期＞基准投资回收期，拒绝接受项目。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]