[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982576":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982576,712,1,"单选题","施工准备阶段，监理单位应负责的活动不包括()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按监理合同要求人员到位，清晰分工与责任",false,{"key":16,"text":17,"correct":14},"B","编制监理规划及实施细则，并与施工单位交底并达成一致",{"key":19,"text":20,"correct":21},"C","编写开工申请报告，上报审批",true,{"key":23,"text":24,"correct":14},"D","办理项目在质量监督站或其他政府授权部门的质量监督手续","施工准备阶段，监理单位应负责：①按监理合同要求人员到位，清晰分工与责任；②编制监理规划及实施细则，并与施工单位交底并达成一致；③熟悉项目图纸；④与业主良好沟通，建立正常联系机制；⑤办理项目在质量监督站或其他政府授权部门的质量监督手续。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]