[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982574,712,1,"单选题","竣工验收阶段，主要管理活动不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","业主组织实施竣工验收的各项准备工作",false,{"key":16,"text":17,"correct":14},"B","竣工验收通过之后，办理竣工结算",{"key":19,"text":20,"correct":14},"C","竣工验收通过之后，办理工程移交（含竣工资料）及保修手续",{"key":22,"text":23,"correct":24},"D","办理政府授权部门的质量监督审查",true,"竣工验收阶段，主要管理活动包括：业主组织实施竣工验收的各项准备工作。在整个施工过程已按设计要求全部完成和试运转合格之后，且预验结果符合工程项目竣工验收标准的前提下，组织竣工验收。竣工验收通过之后，办理竣工结算和工程移交（含竣工资料）及保修手续。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]