[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982569,712,1,"单选题","某项目第一年初投资1500万元，预计第一年末净盈利1100万元，第二年末净盈利1210万元。如果年折现率为10%，则该项目前两年的净现值为()万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","500",true,{"key":16,"text":17,"correct":18},"B","600",false,{"key":20,"text":21,"correct":18},"C","700",{"key":23,"text":24,"correct":18},"D","810","设投资项目第t年的现金流入为CI t ，现金流出为CO t ，基准收益率为i c ，项目计算期为n，则投资项目的财务净现值为：FNPV= 。该项目前两年的净现值为：1100\u002F(1+10%)+1210\u002F(1+10%) 2 -1500=500（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]