[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982565":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982565,712,1,"单选题","管理咨询方根据业主委托方式选择介入工程建设项目的时机。“建造全过程管理”是指管理咨询方在()阶段即介入项目管理。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目建议书",false,{"key":16,"text":17,"correct":18},"B","设计与计划",true,{"key":20,"text":21,"correct":14},"C","施工",{"key":23,"text":24,"correct":14},"D","可行性研究","业主在项目的工程设计与计划阶段才委托管理咨询单位介入项目管理，承担项目工程设计管理与预控计划的编制工作，并延续至项目的竣工及保修责任期，因管理咨询单位在此情况下介入了四阶段表达方式所述“工程设计与计划阶段”和“施工阶段”或三阶段表达方式所述项目“建造期”或“建设期”的完全管理，管理咨询单位所承担的管理被国际工程管理界称为“建造全过程管理”。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]