[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982563,712,1,"单选题","初步的专业工程进度计划是由()编制的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总承包商",false,{"key":16,"text":17,"correct":14},"B","业主",{"key":19,"text":20,"correct":21},"C","各专业工程分包商",true,{"key":23,"text":24,"correct":14},"D","管理咨询单位","初步的专业工程进度计划是由各专业工程分包商在投标时根据招标文件列明的进度管理要求编制的本专业工程的进度计划。在招标文件中要求专业工程的投标人编制此计划是为了避免专业分包商受角色局限，不从项目整体角度而只从自己的角度去看待并安排本专业工程的实施。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]