[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982562":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982562,712,1,"单选题","工程建设项目职业健康安全与环境管理的经济性的主要表现不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程项目是特定时代的反映",false,{"key":16,"text":17,"correct":14},"B","建设工程产品是否应适应可持续发展的要求",{"key":19,"text":20,"correct":14},"C","建设工程应考虑建造成本和其寿命周期内使用成本消耗",{"key":22,"text":23,"correct":24},"D","工程项目的实施需要进行大量的横向配合和协调",true,"工程建设项目职业健康安全与环境管理的经济性主要受产品的时代性和社会性的影响，其主要表现为：①工程项目是特定时代的反映；②建设工程产品是否应适应可持续发展的要求；③建设工程不仅应考虑建造成本的消耗，还应考虑其寿命周期内使用成本消耗。D项属于协调性的主要表现。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]