[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982551,712,1,"单选题","在项目的施工阶段，业主的管理工作内容不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度控制",false,{"key":16,"text":17,"correct":18},"B","质量控制",true,{"key":20,"text":21,"correct":14},"C","采购与合同管理",{"key":23,"text":24,"correct":14},"D","投资控制","在项目的施工阶段，业主的管理工作内容包括：①进度控制；②采购与合同管理；③投资控制；④组织与协调；⑤现场安全文明管理；⑥市政公用工程管理。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]