[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982547,712,1,"单选题","直接影响工程建设项目环境的主要因素是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工准备",false,{"key":16,"text":17,"correct":14},"B","施工验收",{"key":19,"text":20,"correct":21},"C","施工过程",true,{"key":23,"text":24,"correct":14},"D","竣工验收","工程建设项目的环境管理主要体现在项目设计方案和施工环境的控制。项目设计方案在施工工艺的选择方面对环境的间接影响明显，施工过程则是直接影响工程建设项目环境的主要因素。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]