[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982544":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982544,712,1,"单选题","工程建设项目设计准备阶段，业主方项目管理的重要工作之一是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制并报批项目建议书",false,{"key":16,"text":17,"correct":18},"B","确定项目的方案设计",true,{"key":20,"text":21,"correct":14},"C","编制项目进度总控计划",{"key":23,"text":24,"correct":14},"D","进行施工招标","设计准备阶段是指自获得项目建议书批复到项目可行性研究报告获得批复的过程，这一阶段中将进行两大类工作：①项目功能需求（工艺设计）的详尽认证，形成方案设计（工程方案）任务书，最终获得多个可用的设计方案（工程方案）；②编制项目可行性研究报告，最终经技术与经济的综合比选，在上述多个可用方案或多条技术路线中确定最优、最可行的设计方案（工程方案），从而完成可行性研究报告的编制、评审与批复。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]