[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982539,712,1,"单选题","下列可以减少设计与施工在合同上的工作界面的项目管理模式为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","DBB",false,{"key":16,"text":17,"correct":14},"B","CM",{"key":19,"text":20,"correct":14},"C","MC",{"key":22,"text":23,"correct":24},"D","EPC",true,"EPC减少了设计与施工在合同上的工作界面，从而解除了承包商因招标图纸出现错误进行索赔的权力，同时排除了承包商在进度管理上与业主及咨询公司可能产生的纠纷，因而在包干总费用及总工期上非常确定。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]