[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982529,712,1,"单选题","下列关于施工过程的说法错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工过程的最终目的是要建造、恢复、改建、移动或拆除工业、民用建筑和构筑物的全部或一部分",false,{"key":16,"text":17,"correct":14},"B","施工过程一般是在业主组织和授权下，由施工企业具体实施的具有特定目标的一次性活动",{"key":19,"text":20,"correct":21},"C","施工过程的范围一般由项目管理者授予的工程承包合同界定",true,{"key":23,"text":24,"correct":14},"D","施工过程又称施工项目，是指在建设工地范围内所进行的各种生产活动","C项，施工过程的范围一般由业主授予的工程承包合同界定。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]