[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982522":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982522,712,1,"单选题","工程建设项目施工阶段，监理不到位或工作效率低下属于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管理风险",true,{"key":16,"text":17,"correct":18},"B","组织风险",false,{"key":20,"text":21,"correct":18},"C","技术风险",{"key":23,"text":24,"correct":18},"D","质量风险","管理风险的风险因素主要包括：①分包商过多，管理能力不足；②项目领导班子内部管理制度不完善，对工期、质量、进度、安全等指标落实不到位；③监理不到位或工作效率低下。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]