[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982520":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982520,712,1,"单选题","工程建设项目施工质量检查验收时，一般不包括对()的检查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工组织设计",true,{"key":16,"text":17,"correct":18},"B","分部分项工程内容",false,{"key":20,"text":21,"correct":18},"C","工程外观质量",{"key":23,"text":24,"correct":18},"D","施工质量保证资料","建设工程施工质量检查评定验收的基本内容及方法包括：①检验批、分部分项工程内容的抽样检查；②施工质量保证资料的检查，包括施工全过程的技术质量管理资料，其中又以原材料、施工检测、测量复核及功能性试验资料为重点检查内容；③工程外观质量的检查和确认。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]