[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982519":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982519,712,1,"单选题","下列各项中，关于工程计价说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对工程建设项目的计价是采用先汇总，后分解的方式进行",true,{"key":16,"text":17,"correct":18},"B","工程计价可大致划分计量和计价两个环节",false,{"key":20,"text":21,"correct":18},"C","计价程序和计价方法具有特殊性",{"key":23,"text":24,"correct":18},"D","分解结构层次越多，基本子项划分越细，工程造价的计算也更精确","A项，对工程建设项目的计价是采用先分解，后汇总的方式进行，即首先将整个工程建设项目分解为基本构造单元（定额或清单项目），然后根据技术经济参数及价格信息计算出所有基本构造单元的费用并进行组合汇总，最终计算出工程总造价。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]