[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982517":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982517,712,1,"单选题","关于项目施工阶段市政公用工程管理，下列描述错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","办理工程与生产设备的移交手续",true,{"key":16,"text":17,"correct":18},"B","办理土地征用、建设用地规划及建设工程规划等有关手续",false,{"key":20,"text":21,"correct":18},"C","办理施工许可等手续",{"key":23,"text":24,"correct":18},"D","落实建设场地“四通一平”","项目施工阶段市政公用工程管理的内容包括：①落实建设场地“四通一平”；②办理土地征用、建设用地规划及建设工程规划等有关手续；③办理施工许可等手续；④办理水、电、供热、煤气、天然气、通信的供给手续；⑤向各政府主管部门办理各项竣工入住事项；⑥向政府主管部门办理其他各项审批事项。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]