[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982513":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982513,712,1,"单选题","因承包人原因造成的超过合同工程范围的施工或返工所涉及的工程量应该()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","据实计量",false,{"key":16,"text":17,"correct":14},"B","酌情计量",{"key":19,"text":20,"correct":21},"C","不予以计量",true,{"key":23,"text":24,"correct":14},"D","按时计量","采用单价合同时，工程量应按照承包人为履行合同所实际完成的工程量进行计量和确定。施工阶段进行工程计量时，若发现招标工程量清单中出现缺漏项、工程量计算偏差、合同变更、现场条件变化、现场签证等原因引起工程量的增减变化均应据实计量和按实调整。但要注意，因承包人原因造成的超过合同工程范围的施工或返工所涉及的工程量不应予以计量。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]