[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982507":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982507,712,1,"单选题","PEST是一种从政治、经济、社会、技术等四个方面分析项目外部环境的方法，常用于项目风险管理的()过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","风险识别",true,{"key":16,"text":17,"correct":18},"B","风险估计",false,{"key":20,"text":21,"correct":18},"C","风险评价",{"key":23,"text":24,"correct":18},"D","风险处置","风险识别是风险分析的基础，其目的是减少工程建设项目构成的不确定性。风险识别的关键是确保风险识别结果的充分性，常用的识别方法有PEST分析、故障树法、专家调查法、幕景分析方法等。AB两项，工程担保和工程保险都属于转移风险；C项，工程担保是将风险转移给第三方的途径，工程保险是借助第三方来转移风险。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]