[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982505,712,1,"单选题","下列关于进度计划的说法正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目子系统进度计划属于按进度计划的功能性不同划分的类型",false,{"key":16,"text":17,"correct":14},"B","设计进度计划属于按进度计划所涉及的工程建设项目阶段的不同划分的类型",{"key":19,"text":20,"correct":21},"C","项目进度总体规划属于按进度计划编制的深度划分的类型",true,{"key":23,"text":24,"correct":14},"D","年度或跨年度进度计划属于按进度计划编制主体的不同划分的类型","A项，项目子系统进度计划属于按进度计划编制的深度划分的类型。B项，设计进度计划是按进度计划编制主体的不同划分的类型；D项，年度或跨年度进度计划是按进度计划所涉及的工程建设项目阶段的不同划分的类型。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]