[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982503":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982503,712,1,"单选题","下列各项中，()不属于工程建设项目质量验收实施主体。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":14},"C","设计单位",{"key":22,"text":23,"correct":24},"D","政府部门",true,"工程建设项目质量验收包括工程施工质量的过程验收和竣工验收两个部分。实施主体包括建设单位和监理、设计、施工单位等。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]