[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982498":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982498,712,1,"单选题","可用以在约束条件下确定项目各项活动最早、最晚的开始和完成时间的方法是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键路径法",true,{"key":16,"text":17,"correct":18},"B","PERT图",false,{"key":20,"text":21,"correct":18},"C","横道图法",{"key":23,"text":24,"correct":18},"D","网络图","关键路径法的基本原理是用网络图表达项目活动之间的相互关系和进度，并在此基础上进行网络分析，计算网络中各项时间参数，确定关键活动与关键路线，利用时差调整与优化网络，求得最短工期。同时，考虑成本与资源问题，以求得项目计划方案的综合优化。关键路径法可用以在约束条件下确定项目各项活动最早、最晚的开始和完成时间。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]