[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982490":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982490,712,1,"单选题","为了有效地实施项目的绩效管理及考核，对项目团队及成员进行绩效考核的管理目标与标准应在()中确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目绩效管理计划",true,{"key":16,"text":17,"correct":18},"B","绩效沟通",false,{"key":20,"text":21,"correct":18},"C","团队组建",{"key":23,"text":24,"correct":18},"D","薪酬管理","项目绩效管理计划是绩效管理过程的起点，强调通过互动式的沟通手段，使高层管理者和项目团队成员在如何实现预期绩效的问题上达成共识。作为项目绩效管理过程的起点，对外，项目发起人要与项目经理和管理团队达成明确项目管理目标及考核管理目标是否实现的协议；对内，项目经理要与全体团队成员共同研究确定每一成员在各个工作阶段该做什么工作，达到什么标准和质量，以及如何进行考核奖惩。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]