[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982484":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982484,712,1,"单选题","项目组合管理采取的是()的管理方式。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自下而上",false,{"key":16,"text":17,"correct":18},"B","自上而下",true,{"key":20,"text":21,"correct":14},"C","由内到外",{"key":23,"text":24,"correct":14},"D","由外到内","项目组合管理采取的是自上而下的管理方式，即先确定组织的战略目标，优先选择符合组织战略目标的项目，在组织的资金和资源能力范围内有效执行项目。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]