[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982483":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982483,712,1,"单选题","按照项目生命周期的四阶段划分方式，属于执行和控制阶段工作内容的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","制订项目总体目标",false,{"key":16,"text":17,"correct":14},"B","成立项目基本组织",{"key":19,"text":20,"correct":21},"C","进行项目细节设计",true,{"key":23,"text":24,"correct":14},"D","总结项目执行情况","执行和控制阶段需要进行项目的细节设计，并完成项目的生产。有时也将细节设计与生产行为作为两个阶段。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]