[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982482":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982482,712,1,"单选题","承包商一定会明确固定的开始时间与结束时间，一旦按期结束项目即已完成，而不会周而复始地进行，这体现项目的()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不断完善的渐进性",false,{"key":16,"text":17,"correct":14},"B","特定成果与目标的唯一性",{"key":19,"text":20,"correct":21},"C","临时的一次性",true,{"key":23,"text":24,"correct":14},"D","存在风险的不确定性","临时性是指项目有确切的开始时间与结束时间。当项目目标已实现或项目目标不可能实现，或实施项目的需求已不存在时，项目终止。临时性并不意味着项目历时短，而主要是指项目是有始有终的过程。例如承包商在某时、某地为某业主建造一栋新房子，该承包商的行为一定会有明确的开始时间与结束时间。一旦工作结束项目即已完成，而不会周而复始地进行。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]