[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982477":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982477,712,1,"单选题","项目管理目标的“四重约束”是指()之间的相互约束。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","范围、时间、费用、资源",true,{"key":16,"text":17,"correct":18},"B","范围、进度、资源、造价",false,{"key":20,"text":21,"correct":18},"C","质量、安全、环境、时间",{"key":23,"text":24,"correct":18},"D","安全、质量、造价、时间","项目的目标是对项目所要达到的最终状态的描述，包括满足范围、时间、费用和资源约束条件。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]