[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982475":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982475,712,1,"单选题","在项目生命周期中，项目所面临风险的变化规律是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目开始阶段风险较小，此后逐渐增大，结束阶段又迅速减小",false,{"key":16,"text":17,"correct":14},"B","项目开始阶段风险较大，此后逐渐降低，结束阶段又迅速增大",{"key":19,"text":20,"correct":14},"C","随着项目推进，风险逐渐增大",{"key":22,"text":23,"correct":24},"D","随着项目推进，风险逐渐减小",true,"参见第3题解析。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]