[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982473":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982473,712,1,"单选题","项目生命周期按四阶段划分时，下列工作内容中，属于计划阶段的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成立项目基本组织",false,{"key":16,"text":17,"correct":14},"B","进行项目细节设计",{"key":19,"text":20,"correct":14},"C","提出项目概念",{"key":22,"text":23,"correct":24},"D","制定项目基本目标",true,"项目的生命周期一般被划分为四到六个阶段，分别是：①开始阶段（项目启动与提出项目概念阶段）；②计划阶段（项目规划、开发与论证决策阶段）；③执行和控制阶段（项目执行或管理执行阶段）；④结束阶段（终结和收尾阶段）。其中，在计划阶段，根据前一阶段提出的项目概念做出具体研究和规划，制订项目的各项目标，再由项目发起人和业主对此审核论证、认定。有时也将规划开发与审核论证决策作为两个阶段。AC两项属于开始阶段的工作；B项属于项目执行和控制阶段的工作。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]