[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982465":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982465,712,1,"单选题","项目总体管理目标应由()制订。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目总承包单位",false,{"key":16,"text":17,"correct":14},"B","政府主管部门",{"key":19,"text":20,"correct":21},"C","项目发起人",true,{"key":23,"text":24,"correct":14},"D","项目招标代理机构","项目总体管理目标的制订只能由项目发起人承担，其他的参与方只能在自己的合同与责任范围内制订子项目或相应部分的分解管理目标，且分解的目标不能与项目总体目标产生冲突。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]