[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982457":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982457,712,1,"单选题","按照PDCA方法循环开展项目质量管理工作时，P阶段的工作内容是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定质量改进目标，制订改进措施",false,{"key":16,"text":17,"correct":18},"B","明确质量目标，提出质量管理程序",true,{"key":20,"text":21,"correct":14},"C","采取应急措施，解决质量问题",{"key":23,"text":24,"correct":14},"D","规范质量行为，组织实施质量计划","通用的过程动态管理方法为PDCA循环方法，其中，计划(Plan)阶段的工作内容是，针对项目或过程目标制订相关目标、程序、方法和详细计划。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]