[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982456":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982456,712,1,"单选题","与工程建设项目进度计划不同，招标采购进度计划必须()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","保证服务效果满足客户明确的需要",false,{"key":16,"text":17,"correct":18},"B","服从于整体项目进度要求",true,{"key":20,"text":21,"correct":14},"C","保证服务效果满足客户隐含的需要",{"key":23,"text":24,"correct":14},"D","适应采购项目管理组织方式","招标采购属于整体项目管理的一部分，其进度计划必须服从于整体项目进度要求，所以招标采购活动往往具有较为严格的进度要求。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]