[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982455":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982455,712,1,"单选题","招标采购项目进度管理中，确定招标工作排序的基础性工作是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目采购时间要求",false,{"key":16,"text":17,"correct":14},"B","采购工作持续时间",{"key":19,"text":20,"correct":14},"C","采购工作资源条件",{"key":22,"text":23,"correct":24},"D","制订项目招标工作内容",true,"确定招标工作排序的基本步骤包括：①制订项目招标工作内容；②研究项目特性；③确定各项工作内容之间的工艺关系；④明确组织关系；⑤研究实施条件和外部制约因素。其中，制订项目招标工作内容是确定招标工作排序的基础性工作。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]