[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982451":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982451,712,1,"单选题","()是保证项目招标采购成功、降低项目风险的重要标志。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","对投资的控制标准",false,{"key":16,"text":17,"correct":14},"B","对投资的控制结果",{"key":19,"text":20,"correct":14},"C","对项目的质量、进度和成本的控制标准",{"key":22,"text":23,"correct":24},"D","对项目的质量、进度和成本的控制结果",true,"招标人（或代理机构）在编制招标方案和实施过程中，对项目的质量、进度和成本的控制结果不仅体现了采购团队工作质量和水平，而且是保证项目招标采购成功、降低项目风险的重要标志。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]