[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982448":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982448,712,1,"单选题","下列关于招标方案的制订说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标方案的制订需要在招标采购实施启动前做好",false,{"key":16,"text":17,"correct":18},"B","大、中型项目的招标采购，招标方案可以与招标采购项目管理方案合一",true,{"key":20,"text":21,"correct":14},"C","招标方案针对所采购对象，可区分招标类型或标段（合同包）分开进行",{"key":23,"text":24,"correct":14},"D","招标方案编制中应及时调整招标方案并启动项目管理的“变更程序”","B项，对于一些简单项目的单次招标采购，招标方案可以与招标采购项目管理方案合一；对于大、中型项目或技术复杂、专业性强的招标，应单独编制书面的招标方案。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]