[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982447,712,1,"单选题","在招标代理工作的责任分配矩阵中，采用字母来表示工作参与角色或责任时，字母D代表()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","执行工作",false,{"key":16,"text":17,"correct":14},"B","控制进度",{"key":19,"text":20,"correct":14},"C","需要培训工作",{"key":22,"text":23,"correct":24},"D","单独或决定性决策",true,"在招标采购项目管理的责任分配矩阵中，采用字母来代表工作参与角色或责任时，X表示执行工作；d表示部分或参与决策；C表示必须咨询的；I表示必须通报的；D表示单独或决定性决策。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]