[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982443":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982443,712,1,"单选题","编制招标采购项目进度计划时，不作为编制依据的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","各项工作的时间估计",false,{"key":16,"text":17,"correct":14},"B","项目采购的技术经济条件",{"key":19,"text":20,"correct":14},"C","法律法规的时限规定",{"key":22,"text":23,"correct":24},"D","项目经理的权限和责任",true,"制订进度计划的依据主要包括：①项目采购时间要求；②项目采购的特点；③项目采购的技术经济条件；④招标采购各项工作的时间估计；⑤限制和约束。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]