[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982436":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982436,712,1,"单选题","为实现招标采购项目成本控制目标，应采取的措施包括()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确保招标文件系统严谨、逻辑合理",false,{"key":16,"text":17,"correct":14},"B","定期对里程碑计划的执行进行检查",{"key":19,"text":20,"correct":21},"C","采用项目群管理方式合理安排人力资源",true,{"key":23,"text":24,"correct":14},"D","掌握项目总体进度对招标采购工作时间的要求","为实现招标采购成本控制（费用控制）目标，应采取的措施主要包括：①采购团队应合理安排人力资源、避免间歇式工作、采用招标项目群管理方式；②充分利用信息和共享资源；③建立费用管理（申报、报销等）制度、标准及审核、审批程序以及厉行节约；④减少额外费用支出。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]