[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982432":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982432,712,1,"单选题","进度管理中进度安排要素的主要内容不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进度编制",false,{"key":16,"text":17,"correct":14},"B","时间估计",{"key":19,"text":20,"correct":14},"C","成本估计",{"key":22,"text":23,"correct":24},"D","进度目标细化",true,"进度管理中进度安排要素主要内容有：①进度编制；②时间估计；③成本估计；④项目的开始和结束日期。D项属于进度管理中工作分解的内容。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]