[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982420":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982420,712,1,"单选题","招标采购项目进度计划的编制步骤是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目背景描述→组建采购团队→确定合同包的划分→进度计划制定→平衡各工作管理因素的相互关系",false,{"key":16,"text":17,"correct":18},"B","确定各项工作的先后顺序→估计出各工作的延续时间→确定招标采购工作的时间进度→平衡各工作管理因素的相互关系→应用相关工具编制进度计划",true,{"key":20,"text":21,"correct":14},"C","平衡各工作管理因素的相互关系→工作结构分解→确定工作逻辑关系→估计工作持续时间→进度计划制定",{"key":23,"text":24,"correct":14},"D","招标工作列表→项目特性描述→确定工作逻辑关系→估计工作持续时间→应用相关工具编制进度计划","招标进度计划是表达招标采购工作中各项工作的开展顺序、开始和完成时间以及相互衔接关系的计划，具体编制步骤有：①根据招标采购工作内容的分解，确定各项工作的先后顺序；②估计出各工作的延续时间；③确定招标采购工作的时间进度；④平衡各工作管理因素的相互关系；⑤应用相关工具（如关键路径法、横道图）编制进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]