[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982416":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982416,712,1,"单选题","业主拟采购一套精密设备，考虑到采购过程有一定的技术难度，选择了有丰富的类似设备采购经验的一家招标代理机构，这属于风险应对策略中的()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","风险规避",false,{"key":16,"text":17,"correct":14},"B","风险转移",{"key":19,"text":20,"correct":14},"C","风险自留",{"key":22,"text":23,"correct":24},"D","风险降低",true,"减轻风险是招标采购与合同管理风险控制的常用方法之一。减轻风险包括风险分散、风险分离、风险监测、后备应急措施等。例如，在招标采购过程中，委托资质等级高并有同类项目采购业绩经验的招标代理机构代理招标，就属于降低风险的有效方式。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]