[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982391":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982391,712,1,"单选题","下列关于项目采购管理内容的说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","从项目组织内部获得服务。",true,{"key":16,"text":17,"correct":18},"B","从项目组织外部采购产品",false,{"key":20,"text":21,"correct":18},"C","合同由具有相应权限的项目团队成员签发",{"key":23,"text":24,"correct":18},"D","管理合同或订购单","项目采购管理包括三个过程：①从项目组织外部采购或获得所需产品、服务或成果的过程。②采购合同的履约过程。包括合同管理和变更控制过程。通过这些过程，编制合同或订购单，并由具备相应权限的项目团队成员加以签发，然后再对合同或订购单进行管理。③内部管理过程。包括有时外部组织为从项目组织内部获取项目产品、服务或成果而签订的合同，以及管理该合同的项目团队应承担的合同义务等。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]