[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982386,712,1,"单选题","下列各项不属于开标前的风险监控内容的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","严格资格预审",false,{"key":16,"text":17,"correct":18},"B","合同履约担保",true,{"key":20,"text":21,"correct":14},"C","科学策划和编制招标文件",{"key":23,"text":24,"correct":14},"D","投标担保","开标前，招标人需要对风险较大的招标因素，包括外部风险（经济、政策风险和地区保护主义的风险）和投标人的风险等因素进行有效控制。主要内容包括：①严格资格预审；②科学策划和编制招标文件；③投标担保。B项属于开标后的风险处置的内容。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]