[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982368":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982368,712,1,"单选题","某网络计划中，A工作有两项紧后工作 B、 C，已知B工作的最迟完成时间为24，持续时间为6；C工作的最迟完成时间为28，持续时间为12，则A工作的最迟完成时间是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","16",true,{"key":16,"text":17,"correct":18},"B","18",false,{"key":20,"text":21,"correct":18},"C","24",{"key":23,"text":24,"correct":18},"D","28","最迟完成（LS）时间是指在完工时间内活动必须完成的最迟时间。题中，LS C =LF C -D C ，B工作的最迟开始时间LS B =LF B -D B =24-6=18,C工作的最迟开始时间LS C =LF C -D C =28-12=16,A工作的最迟完成时间为B、C两工作的最迟开始时间的最小者，即16。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]